Wednesday 4th November a.m.
A client who is having a high end new build completed noticed something on a routine site visit. The installers of a solar array on the roof had routed the DC output cables over the architectural fascia and soffit. In a normal domestic scene this would have been fine, but given the lengths that had been gone to give the house clean modern lines, the client was keen that his architectural vision be retained.
After discussions with the builder and solar guys it was apparent that if the cables were to be routed off the roof via a different method, something would be required that would not compromise the brand new slatework but would provide a permanent no drill solution. To add some pressure to the design team the build schedule required that the scaffolding providing access to the roof was due to be cleared on the Friday, less than 48 hours later.
Thursday 5th November a.m.
We proposed a stainless steel conduit and clamp arrangement that would hug the external frame of a conveniently placed skylight. Feedback from site highlighted that anything attached to the skylight must not interfere with its opening. The design was settled and materials secured from a stockist 50 miles away and collection arranged. The stainless steel arrived on one of our vehicles at 17.30 hrs.
Friday 6th November a.m.
One of our first class welder fabricators got the thing made in short order. By 09.30 it was safely installed on the roof. The scaffolding was removed that afternoon and the project continues on schedule and just as importantly, on vision!
Share via: